(TSX Venture: NOT) is pleased to provide an update on their project
development plans for their Ring of Fire deposits.

    The Project development milestones identified were:

    - Establish feasibility schedules for various project components
    - Initiate socio economic studies
    - Complete environmental baseline and environmental studies
    - Initiate project consultations with First Nations communities
    - Environmental review and permitting
    - Complete marketing and sales studies
    - Define project execution plans including Private Public partnerships
      for infrastructure development

Noront's projects are the most advanced in the Ring of Fire and we
estimate that Feasibility Studies could be completed on the Eagle's Nest
(nickel, copper, PGE's) and the Blackbird (chromite) deposits by the first
quarter of 2011. Due to the different complexities of the two types of
deposits, Noront believes the Eagle's Nest deposits could be put into
production by the first quarter of 2016 while the chromite development is
expected to follow as a result of increased infrastructure requirements.

The main differences in the two time schedules are driven by many
factors, which are largely out of Noront's control. These differences
include:

    - The Eagle's Nest deposit is a much higher grade deposit and as a
      result can withstand additional inventory costs and could likely be
      developed with seasonal access;
    - The Blackbird chromite deposits, along with other chromite deposits
      in the region, will require significant infrastructure development in
      order to be economic;
    - The chromite deposits will require the development of all season
      access that will require the evaluation of numerous options, for both
      routing and mode of transportation, and will require extensive
      consultation with First Nations communities;
    - The subsequent development of a ferrochrome smelter will require
      extensive environmental review and will be further complicated by the
      requirement of significant power supply in the order of 400-500 mega
      watts; and
    - Noront's due diligence shows that it is unlikely that Ontario's
      current power generation or transmission capacity can handle this
      expanded electrical load and the development of the power supply
      project alone is likely to extend the ferrochrome project past 2016.

    Noront is confident in the project milestones currently established and
    in support of achieving these milestones has taken the following steps:

    - Engaged SNC Lavalin to complete a transportation study that includes
      numerous routes and modes of transportations. SNC Lavalin is expected
      to finalize the feasibility study on the preferred routes and mode of
      transportation, as well as the other alternatives considered, by the
      fourth quarter of 2010. This work, including the evaluation of
      alternatives, will be a significant part of the project approvals and
      consultation process;
    - Environmental baseline studies are currently underway;
    - NI 43-101 resource reports have been initially completed for Eagle's
      Nest and are being finalized for Blackbird and as a result we are
      confident that our procedures and quality analysis and quality
      control protocols will meet or exceed industry standards;
    - Noront is currently reviewing qualifications from various contractors
      in support of the feasibility studies and expects to have all major
      contractors engaged by early 2010; and
    - Through discussions with our First Nations Advisory Board, Noront is
      developing a consultation schedule and intends to initiate the
      consultation process with the First Nations communities in the first
      quarter of 2010. This will include the expansion of consultations as
      project definitions are finalized during the feasibility study
      process.

Mr. Paul Semple P. Eng, Noront's Chief Operating Officer stated, "The
development plans and schedules we are currently proposing are based on
months of strategic planning and numerous conversations with First Nations
leaders, industry professionals and Federal and Provincial government
officials. We are confident of the schedules that we are proposing for the
nickel copper projects and at the same time we intend to work diligently on
developing the more complex chromite projects. These projects are
multifaceted and will require extensive consultations, discussions and
negotiations. Until we complete these steps, we cannot responsibly report
on the development plans including the capital costs, schedule or the project
economics of the Ring of Fire chromite deposits." Mr. Semple further stated,
"Based on Noront's due diligence regarding the chromite market, the technical
demands of a ferrochrome project, the unknown aspects of the permitting
process, the complexity of developing a large infrastructure project
especially as a private public partnership along with the current the status
of Ontario's infrastructure, we currently believe that the project costs,
scope, smelter location, project economics or development timeline can not be
accurately forecast or estimated. We believe any forecasts on the chromite
projects, at this stage, absent of a project definition being completed,
consultation with impacted First Nations being initiated and intensive
discussions with the Provincial and Federal governments is purely
speculation."

About Noront

Noront Resources Ltd. is focused on its significant and multiple,
high-grade nickel-copper-platinum-palladium, chromite, gold and vanadium
discoveries in an area known as the "Ring of Fire", an emerging multi-metals
district located in the James Bay Lowlands of Ontario, Canada. Noront is the
dominant land holder at the Ring of Fire and continues to delineate and prove
up its discoveries with NI 43-101 technical and economic reports and an
aggressive and well financed drill plan for the remainder of 2009 and 2010.
All material information on Noront can be found on the Company's website at
www.norontresources.com or at SEDAR at www.sedar.com.

Wesley (Wes) Hanson

President & Chief Executive Officer

FORWARD LOOKING STATEMENTS

This release contains "forward-looking statements" within the meaning of
applicable Canadian securities legislation, including predictions,
projections and forecasts. Forward-looking statements include, but are not
limited to, statements that address activities, events or developments that
the Company expects or anticipates will or may occur in the future, including
such things as future business strategy, competitive strengths, goals,
expansion, growth of the Company's businesses, operations, plans and with
respect to exploration results, the timing and success of exploration
activities generally, permitting time lines, government regulation of
exploration and mining operations, environmental risks, title disputes or
claims, limitations on insurance coverage, timing and possible outcome of
any pending litigation and timing and results of future resource estimates
or future economic studies.

Often, but not always, forward-looking statements can be identified by
the use of words such as "plans", "planning", "planned", "expects" or
"looking forward", "does not expect", "continues", "scheduled", "estimates",
"forecasts", "intends", "potential", "anticipates", "does not anticipate", or
"belief", or describes a "goal", or variation of such words and phrases or
state that certain actions, events or results "may", "could", "would",
"might" or "will" be taken, occur or be achieved.

Forward-looking statements are based on a number of material factors and
assumptions, including, the result of drilling and exploration activities,
that contracted parties provide goods and/or services on the agreed
timeframes, that equipment necessary for exploration is available as
scheduled and does not incur unforeseen break downs, that no labour shortages
or delays are incurred, that plant and equipment function as specified, that
no unusual geological or technical problems occur, and that laboratory and
other related services are available and perform as contracted.
Forward-looking statements involve known and unknown risks, future events,
conditions, uncertainties and other factors which may cause the actual
results, performance or achievements to be materially different from any
future results, prediction, projection, forecast, performance or achievements
expressed or implied by the forward-looking statements. Such factors include,
among others, the interpretation and actual results of current exploration
activities; changes in project parameters as plans continue to be refined;
future prices of gold; possible variations in grade or recovery rates;
failure of equipment or processes to operate as anticipated; the failure of
contracted parties to perform; labour disputes and other risks of the mining
industry; delays in obtaining governmental approvals or financing or in the
completion of exploration, as well as those factors disclosed in the
company's publicly filed documents. Although Noront has attempted to identify
important factors that could cause actual actions, events or results to
differ materially from those described in forward-looking statements, there
may be other factors that cause actions, events or results not to be as
anticipated, estimated or intended. There can be no assurance that
forward-looking statements will prove to be accurate, as actual results
and future events could differ materially from those anticipated in such
statements. Accordingly, readers should not place undue reliance on
forward-looking statements.

Neither TSX Venture Exchange nor its Regulation Services Provider (as
that term is defined in the policies of the TSX Venture Exchange) accepts
responsibility for the adequacy or accuracy of this release.

For further information: regarding this Offer, please contact Wes Hanson,
President and Chief Executive Officer or Joanne Jobin, Vice President
Corporate Communications at +1-416-367-1444, or visit Noront's website at:
www.norontresources.com/

For further information: regarding this Offer, please contact Wes Hanson, President and Chief Executive Officer or Joanne Jobin, Vice President Corporate Communications at +1-416-367-1444

YOUR VIEW POINT
NAME : (REQUIRED)
MAIL : (REQUIRED)
will not be displayed
WEBSITE : (OPTIONAL)
YOUR
COMMENT :