Gammon Reports Increasing Production at Ocampo in the Second Quarter 2010 - Ocampo Nearing or Exceeding Designed Key Performance Targets
By Gammon Gold Inc., PRNEWednesday, July 14, 2010
HALIFAX, Canada, July 15, 2010 - Gammon Gold Inc. ("Gammon") (TSX:GAM and NYSE:GRS): Gammon is pleased to
provide preliminary second quarter results for its Ocampo mine as well as on
a consolidated basis. All figures reported are in U.S. dollars unless
otherwise indicated.
Second Quarter Ocampo Operational Highlights
- For the second quarter the Ocampo mine reported steadily improving productivity. In the quarter the Ocampo mine produced 24,963 gold ounces and 1,066,998 silver ounces, or 44,363 gold equivalent ounces using the Company's long-term gold-to-silver ratio of 55:1 (41,362 gold equivalent ounces, using the realized gold-to-silver ratio of 65:1). - Total cash costs in the second quarter at Ocampo were $427 per gold equivalent ounce using the Company's long-term gold-to-silver ratio of 55:1 ($459 per gold equivalent ounce, using the realized gold-to-silver ratio of 65:1). - Utilizing Ocampo's silver revenues as a by-product cost credit, second quarter total cash costs were negative $43 per gold ounce. - In comparison to the first quarter, second quarter gold production at Ocampo increased by 14% and silver production increased by 11%, while cash costs declined month over month throughout the second quarter. - Most recently, the Company completed a number of capital projects including: - Commissioning of the three remaining cyclones, which completed the Phase III Ocampo mill expansion program (April). - Commissioning of the seventh thickener was completed in early July and the sixth leach tank will be commissioned within the week. Both items are key components of the Ocampo mill redundancy program and are critical to continued improvements in silver recovery efficiencies. - Installation of an upgraded gear box at the Ocampo overland conveyor system, which is expected to allow the conveyor system to reach the higher end of the targeted rate of between 10-12,000 tonnes per day commencing mid-July. - 154 contract miners, including supervisors, surveyors, geologists and maintenance personnel, as well as 30 pieces of key underground mining fleet equipment from El Cubo have been redeployed to the Ocampo mine to expand underground operations. The workers are currently on site at Ocampo and are part of the regular manning rotation roster. - These additional workers and equipment have been deployed to focus primarily on advancing development at the Santa Eduviges, Belen, San Amado, Jesus Maria, Maria, Molinas Southwest, Rosario, and the southern extensions of Aventurero discoveries. These recent discoveries are not included in the 2009 Reserve and Resources statement. Ocampo Production and Cash Costs(1) Production Q1 2010 Q2 2010 Gold Ounces Produced 21,855 24,963 Silver Ounces Produced 960,817 1,066,998 Gold Equivalency Rate (Realized) 66 65 Gold Eq. Ounces Produced (Realized) 36,546 41,362 Gold Eq. Ounces Produced (55:1)(2) 39,325 44,363 Total Cash Costs Q1 2010 Q2 2010 Cash Costs per Gold Eq. Ounce (Realized)(1) $458 $459 Cash Costs per Gold Eq. Ounce (55:1)(1)(2) $423 $427 Cash Costs per Gold Ounce(1) $8 ($43) (1) Cash costs for the second quarter 2010 have not been finalized and are subject to adjustment (2) Comparative performance metrics using the Company's long term gold equivalency guidance ratio (55:1)
Ocampo Key Performance Indicators Nearing or Exceeding Design Targets
During the second quarter, the Ocampo mine reported
improvements in key operating metrics. The table below presents the
performance on key operational metrics for this period.
Ocampo Key Performance Metrics - Second Quarter 2010 Production Apr-10 May-10 Gold Ounces Produced 6,816 8,467 Silver Ounces Produced 279,445 364,227 Gold Equivalency Rate (Realized) 63 65 Gold Eq. Ounces Produced (Realized) 11,228 14,047 Gold Eq. Ounces Produced (55:1)(2) 11,897 15,089 Total Cash Costs Apr-10 May-10 Cash costs per Gold Eq. Ounce (Realized)(1) 499 450 Cash Costs per Gold Eq. Ounce (55:1)(1)(2) 471 419 Underground Mining Apr-10 May-10 Average tonnes mined per day 1,339 1,368 Head grade Gold (g/t) 1.70 2.20 Head grade Silver (g/t) 102.6 145.4 Ocampo NE underground development (metres) 1,204 1,431 Santa Eduviges development (metres) 194 214 Total underground development (metres) 1,398 1,645 Open Pit Mining Apr-10 May-10 Average tonnes mined per day 104,793 104,128 Head grade Gold (g/t) 0.47 0.48 Head grade Silver (g/t) 25.0 27.3 Milling Apr-10 May-10 Average tonnes milled per day 3,045 3,242 Mill grade Gold (g/t) 1.52 1.62 Mill grade Silver (g/t) 78.5 98.0 Gold recovery (%) 95% 95% Silver recovery (%) 79% 80% Heap Leach Processing Apr-10 May-10 Average tonnes processed per day 8,771 10,726 Head grade Gold (g/t) 0.37 0.38 Head grade Silver (g/t) 21.47 21.02 (continued) Production Jun-10 Q2-2010 Gold Ounces Produced 9,680 24,963 Silver Ounces Produced 423,326 1,066,998 Gold Equivalency Rate (Realized) 66 65 Gold Eq. Ounces Produced (Realized) 16,087 41,362 Gold Eq. Ounces Produced (55:1)(2) 17,377 44,363 Total Cash Costs Jun-10 Q2 2010 Cash costs per Gold Eq. Ounce (Realized)(1) 439 459 Cash Costs per Gold Eq. Ounce (55:1)(1)(2) 406 427 Underground Mining Jun-10 Q2 2010 Average tonnes mined per day 1,490 1,399 Head grade Gold (g/t) 2.70 2.22 Head grade Silver (g/t) 163.0 138.1 Ocampo NE underground development (metres) 1,512 4,147 Santa Eduviges development (metres) 190 598 Total underground development (metres) 1,702 4,745 Open Pit Mining Jun-10 Q2 2010 Average tonnes mined per day 100,396 103,117 Head grade Gold (g/t) 0.57 0.50 Head grade Silver (g/t) 33.5 28.2 Milling Jun-10 Q2 2010 Average tonnes milled per day 3,258 3,182 Mill grade Gold (g/t) 1.99 1.71 Mill grade Silver (g/t) 117.9 98.6 Gold recovery (%) 97% 95% Silver recovery (%) 82% 80% Heap Leach Processing Jun-10 Q2 2010 Average tonnes processed per day 10,529 10,017 Head grade Gold (g/t) 0.43 0.40 Head grade Silver (g/t) 25.16 22.6 (1) Cash costs for the second quarter 2010 have not been finalized and are subject to adjustment (2) Comparative performance metrics using the Company's long term gold equivalency guidance ratio (55:1)
Second Quarter Consolidated Production
As previously disclosed, the Company's consolidated metal
production in the quarter was negatively impacted by an alleged illegal
labour disruption at the El Cubo mine that began on June 2, 2010. As a result
of this disruption, there was negligible production reported from the El Cubo
mine in June. Operations at El Cubo have been suspended indefinitely and the
mine has been placed on care and maintenance.
- On a consolidated basis, the Company produced 29,438 ounces of gold and 1,294,572 ounces of silver, or 52,975 gold equivalent ounces, using the Company's gold-to-silver ratio of 55:1. (49,379 gold equivalent ounces, using the realized gold-to-silver ratio of 65:1). - On a consolidated basis, total cash costs are expected to be $493 per gold equivalent ounce, using the Company's gold-to-silver ratio of 55:1. ($529 per gold equivalent ounce, using the realized gold-to-silver ratio of 65:1). Second Quarter 2010 Consolidated Production and Cash Costs Production Q1 2010 Q2 2010 Gold Ounces Produced 28,431 29,438 Silver Ounces Produced 1,284,071 1,294,572 Gold Equivalency Rate (Realized) 66 65 Gold Eq. Ounces Produced (Realized) 48,061 49,379 Gold Eq. Ounces Produced (55:1)(2) 51,778 52,975 Total Cash Costs Cash costs per Gold Eq. Ounce (Realized)(1) $530 $529 Cash Costs per Gold Eq. Ounce (55:1)(1)(2) $490 $493 Cash Costs per Gold Ounce(1) $125 $62 (1) Cash costs for the second quarter 2010 have not been finalized and are subject to adjustment (2) Comparative performance metrics using the Company's long term gold equivalency guidance ratio (55:1)
About Gammon Gold
Gammon Gold Inc. is a mid-tier gold and silver producer with
properties in Mexico. The Company's flagship Ocampo Project in Chihuahua
State achieved commercial production in January 2007. Gammon Gold also owns
the El Cubo mine in Guanajuato State and has the promising Guadalupe y Calvo
development property in Chihuahua State. The Company recently completed
option purchase agreements to acquire the Mezquite Project in Zacatecas
State, Mexico and the Venus Project located north of the Ocampo mine in
Chihuahua State, Mexico. It also has recently signed a Letter of Intent to
acquire the Los Jarros Project in Chihuahua State, Mexico. Since 2008, the
Company has significantly increased its land position by over 59% and has
made strategic investments in Golden Queen Mining Co. Ltd. and Corex Gold
Corporation. The Company is based in Halifax, Nova Scotia with an Executive
Office in Toronto, Ontario.
For further information please visit the Gammon Gold website
at www.gammongold.com or contact:
Cautionary Statement
Cautionary Note to US Investors - The United States Securities
and Exchange Commission permits US mining companies, in their filings with
the SEC, to disclose only those mineral deposits that a company can
economically and legally extract or produce. This press release uses certain
terms, such as "measured," "indicated," and "inferred" "resources," that the
SEC guidelines strictly prohibit US registered companies from including in
their filings with the SEC. US Investors are urged to consider closely the
disclosure in Gammon Gold's Annual Report on Form 40-F/A, which may be
secured from Gammon Gold, or from the SEC's website at
www.sec.gov/edgar.shtml.
No stock exchange, securities commission or other regulatory
authority has approved or disapproved the information contained herein.
Certain statements included herein, including information as
to the future financial or operating performance of the Company, its
subsidiaries and its projects, constitute forward-looking statements. The
words ''believe'', ''expect'', ''anticipate'', ''contemplate'', ''target'',
''plan'', ''intends'', ''continue'', ''budget'', ''estimate'', "forecast",
''may'', ''will'', ''schedule'' and similar expressions identify
forward-looking statements. Forward-looking statements include, among other
things, statements regarding targets, estimates and assumptions in respect of
gold and silver production and prices, operating costs, results and capital
expenditures, mineral reserves and mineral resources and anticipated grades,
recovery rates, future financial or operating performance, margins, operating
and exploration expenditures, costs and timing of the development of new
deposits, costs and timing of construction, costs and timing of future
exploration and reclamation expenses including, anticipated 2010 and 2011
results, operating performance projections for 2010 and 2011, our ability to
fully fund our business model internally, 2010 and 2011 gold and silver
production and the cash and operating costs associated therewith, the ability
to achieve productivity and operational efficiencies, further improvements to
silver recoveries resulting from improvements to the Ocampo mill and the
timing of each thereof. Forward-looking statements are necessarily based upon
a number of estimates and assumptions that, while considered reasonable by
the Company, are inherently subject to significant business, economic,
competitive, political and social uncertainties and contingencies. Many
factors could cause the Company's actual results to differ materially from
those expressed or implied in any forward-looking statements made by, or on
behalf of, the Company. Such factors include, among others, known and unknown
uncertainties and risks relating to additional funding requirements, reserve
and resource estimates, commodity prices, hedging activities, exploration,
development and operating risks, illegal miners, political and foreign risk,
uninsurable risks, competition, limited mining operations, production risks,
environmental regulation and liability, government regulation, currency
fluctuations, recent losses and write-downs, restrictions in the Company's
loan facility, dependence on key employees, possible variations of ore grade
or recovery rates, failure of plant, equipment or process to operate as
anticipated, accidents and labour disputes. Investors are cautioned that
forward-looking statements are not guarantees of future performance and,
accordingly, investors are cautioned not to put undue reliance on
forward-looking statements due to the inherent uncertainty therein.
Rene Marion Anne Day President and Chief Executive Officer Director of Investor Relations Gammon Gold Inc. Gammon Gold Inc. +1(416)-646-3825 +1(902)-468-0614
Rene Marion, President and Chief Executive Officer, Gammon Gold Inc., +1(416)-646-3825; Anne Day, Director of Investor Relations, +1(902)-468-0614
Tags: canada, Gammon Gold Inc., Halifax, July 15